J. Knaster
ITER
Network
Latest external collaboration on country level. Dive into details by clicking on the dots.
Publication
Featured researches published by J. Knaster.
IEEE Transactions on Applied Superconductivity | 2008
N. Mitchell; D. Bessette; R. Gallix; C. Jong; J. Knaster; P. Libeyre; C. Sborchia; F. Simon
Procurement of the ITER magnets is due to start at the end of 2007/early 2008, with the launch of the longest lead time items, the conductor and the TF coil windings. The base design for procurement was established in 2001, and the build up of the Cadarache ITER team has been accompanied by a review of the most critical, or controversial, features of the 2001 design. At the same time, an urgent R&D program has been launched to complete the necessary verification of the design solutions that are proposed. In this paper an overview will be presented of the main design features and drivers, and some of the recent issues and R&D results will be summarized.
Nuclear Fusion | 2013
J. Knaster; Frederik Arbeiter; P. Cara; P. Favuzza; Tomohiro Furukawa; F. Groeschel; Roland Heidinger; A. Ibarra; H. Matsumoto; A. Mosnier; Hisashi Serizawa; M. Sugimoto; H. Suzuki; E. Wakai
The Engineering Validation and Engineering Design Activities (EVEDA) for the International Fusion Materials Irradiation Facility (IFMIF), an international collaboration under the Broader Approach Agreement between Japan Government and EURATOM, aims at allowing a rapid construction phase of IFMIF in due time with an understanding of the cost involved. The three main facilities of IFMIF (1) the Accelerator Facility, (2) the Target Facility and (3) the Test Facility are the subject of validation activities that include the construction of either full scale prototypes or smartly devised scaled down facilities that will allow a straightforward extrapolation to IFMIF needs. By July 2013, the engineering design activities of IFMIF matured with the delivery of an Intermediate IFMIF Engineering Design Report (IIEDR) supported by experimental results. The installation of a Linac of 1.125 MW (125 mA and 9 MeV) of deuterons started in March 2013 in Rokkasho (Japan). The worlds largest liquid Li test loop is running in Oarai (Japan) with an ambitious experimental programme for the years ahead. A full scale high flux test module that will house ~1000 small specimens developed jointly in Europe and Japan for the Fusion programme has been constructed by KIT (Karlsruhe) together with its He gas cooling loop. A full scale medium flux test module to carry out on-line creep measurement has been validated by CRPP (Villigen).
IEEE Transactions on Applied Superconductivity | 2008
C. Sborchia; Y. Fu; R. Gallix; C. Jong; J. Knaster; N. Mitchell
The current design of the ITER Toroidal Field coils and structures, the main critical design and manufacturing issues, and the status of the procurement arrangements for these components, which will be released to the ITER parties in early 2008 to start the manufacturing contracts, are described. Some qualification and R&D work still required in preparation for the manufacture are also mentioned.
IEEE Transactions on Applied Superconductivity | 2010
F. Savary; Alessandro Bonito-Oliva; R. Gallix; J. Knaster; Norikiyo Koizumi; N. Mitchell; H. Nakajima; K. Okuno; C. Sborchia
The magnet system for ITER comprises 18 Toroidal Field (TF) Coils using Nb3Sn cable-in-conduit superconductor, which operate at 4.5 K in supercritical helium. The procurement of the TF Coils and Structures is amongst the first which have been launched following the creation of the ITER Organization (IO). It is organized in 4 phases. A Procurement Design Readiness Review held in April 2008 confirmed the readiness of the design to proceed with Phases I and II. Procurement Arrangements (PA) were signed with the European and Japanese Domestic Agencies (DA) respectively in June and November 2008. After a brief description of the TF Coils and Structures, the paper gives an overview of the PA showing the milestones towards series production. The procurement strategy of both DA involved is described, in particular the first step which covers pre-production activities: qualification of raw materials, manufacturing trials, mock-ups and full-scale prototype radial plates, impregnation tests and, possibly, winding trials. The work carried out by IO is also presented: optimization of the cover plate welding to satisfy the allowable stress criteria while minimizing the associated distortions, qualification of blends of cyanate ester with epoxy resin for the impregnation of the winding packs and design of the coil terminal region including integration of the needed instrumentation.
IEEE Transactions on Applied Superconductivity | 2012
David Evans; J. Knaster; H. Rajainmaki
The technology associated with the design and construction of superconducting magnets has evolved dramatically over the last three decades leading to an overall increase in their complexity. Their use has moved from particle physics through medical applications such as MRI to the very large magnets demanded by fusion technology, where the optimal quality of the HV insulation is a critical step in achieving the design performance. The Vacuum Pressure Impregnation (VPI) technique-a particularly refined case of the more widely known Vacuum Assisted Resin Transfer Mould (VARTM)-has become the most common process for the consolidating electrical insulation of large superconducting magnets. To achieve success with the VPI process demands that detailed attention is paid to many steps, namely: coil drying, resin degassing and coil impregnation. Commercial sensitivity has meant that there has not been a well-published exchange of information and therefore many details of the VPI process may vary in different organizations. The present paper aims at filling this gap and will discuss in detail: (1) all required steps with the main risks in each of them, (2) commonly used methods in each of the steps for optimized control of the process and (3) tooling to minimize risk of failure during impregnation.
IEEE Transactions on Applied Superconductivity | 2010
E. Baynham; R. Gallix; J. Knaster; N. Mitchell; F. Savary
The ITER TF Coils will consist of two main components; the WP which is formed by the assembly of seven double pancakes, superconducting windings inserted into stainless steel radial plates and the stainless steel structural casing which forms the mechanical interface between TF coils and the remainder of the ITER machine. The final step in assembly of the TF Coils will be the insertion of the WP into the structural casing. The insertion procedure must achieve two critical objectives; accurate geometric location, 1 mm, of the WP current center line with respect to the casing reference faces and the full mechanical location of the WP within the casing to facilitate the uniform transfer of the electromagnetic forces to the casing and the ITER TF keystone structure.
TRANSACTIONS OF THE INTERNATIONAL CRYOGENIC MATERIALS CONFERENCE—ICMC: Advances in Cryogenic Engineering Materials | 2010
J. Knaster; W. Baker; Livio Bettinali; C. Jong; K. Mallick; C. Nardi; H. Rajainmaki; P. Rossi; Luigi Semeraro
The pre‐compression system is the keystone of ITER. A centripetal force of ∼30 MN will be applied at cryogenic conditions on top and bottom of each TF coil. It will prevent the ‘breathing effect’ caused by the bursting forces occurring during plasma operation that would affect the machine design life of 30000 cycles. Different alternatives have been studied throughout the years. There are two major design requirements limiting the engineering possibilities: 1) the limited available space and 2) the need to hamper eddy currents flowing in the structures. Six unidirectionally wound glass‐fibre composite rings (∼5 m diameter and ∼300 mm cross section) are the final design choice. The rings will withstand the maximum hoop stresses <500 MPa at room temperature conditions. Although retightening or replacing the pre‐compression rings in case of malfunctioning is possible, they have to sustain the load during the entire 20 years of machine operation. The present paper summarizes the pre‐compression ring R&D carri...
Review of Scientific Instruments | 2016
Y. Okumura; R. Gobin; J. Knaster; R. Heidinger; Juan Marcos Ayala; Benoit Bolzon; P. Cara; Nicolas Chauvin; Stéphane Chel; Dominique Gex; Francis Harrault; R. Ichimiya; A. Ihara; Y. Ikeda; Atsushi Kasugai; T. Kikuchi; T. Kitano; Masao Komata; K. Kondo; S. Maebara; Alvaro Marqueta; Shigeru O’hira; M. Perez; G. Phillips; G. Pruneri; K. Sakamoto; F. Scantamburlo; Franck Senée; K. Shinto; M. Sugimoto
The objective of linear IFMIF prototype accelerator is to demonstrate 125 mA/CW deuterium ion beam acceleration up to 9 MeV. The injector has been developed in CEA Saclay and already demonstrated 140 mA/100 keV deuterium beam [R. Gobin et al., Rev. Sci. Instrum. 85, 02A918 (2014)]. The injector was disassembled and delivered to the International Fusion Energy Research Center in Rokkasho, Japan. After reassembling the injector, commissioning has started in 2014. Up to now, 100 keV/120 mA/CW hydrogen and 100 keV/90 mA/CW deuterium ion beams have been produced stably from a 10 mm diameter extraction aperture with a low beam emittance of 0.21 π mm mrad (rms, normalized). Neutron production by D-D reaction up to 2.4 × 10(9) n/s has been observed in the deuterium operation.
IEEE Transactions on Applied Superconductivity | 2012
Alessandro Bonito Oliva; Alessandro Formisano; J. Knaster; Raffaele Martone; A. Portone; Pietro Testoni
The Toroidal Field Coils (TFC) are subject to mandatory geometrical tolerances constraints for acceptance by ITER Organization. As a consequence, pre-assembly tests are foreseen to verify if each single coil meets such criteria, including laser tracking, and possibly warm magnetic measurements on each of the finished winding packs. Possible performance limitations of the acceptance tests for the winding pack are assessed in this paper. Since construction details are not presently known, the paper proposes an assessment of the mathematical and numerical tools able to perform the final evaluation of the actual feasibility of magnetic testings and discusses their performance in terms of accuracy and reliability.
IEEE Transactions on Applied Superconductivity | 2012
F. Savary; R. Gallix; J. Knaster; N. Mitchell; Kazutaka Seo
The ITER Magnet System contains 18 Toroidal Field Coils (TFC). These are large D-shaped coils of about 300 t, 17.5-m height and 9-m width. They consist of a Winding Pack (WP) enclosed in a rigid structural steel case, the Toroidal Field Coil Case (TFCC). The WP is a bonded structure of 7 Double Pancakes (DP), each made up of a radial plate (RP) housing the reacted cable-in-conduit superconductor (CICC), which operate at 4.5 K in supercritical helium. The conductor carries a current of 68 kA in operation to produce a nominal peak field of 11.8 T. The total stored magnetic energy in the 18 TFCs is 41 GJ. While the Japanese and European Domestic Agencies that are in charge of the procurement of the TFCs are progressing with the manufacturing design and the fabrication trials prior to launch the production of the real coils, the ITER Organization (IO) is completing the development and qualification of the most critical items, e.g. cyanate ester and resin blends for the conductor and WP insulation system, the terminal region, the helium inlet, a charged resin system for the filling of the gap between the WP and the TFCC and the general tolerancing especially at the interfaces between the neighboring systems. This paper presents the final design of the TFCs and the results of the developments carried out in the aforementioned areas in the last 2 years.